Ksyen Regional Hospital - Terrace, BC

Share Ksyen Regional Hospital - Terrace, BC on Facebook Share Ksyen Regional Hospital - Terrace, BC on Twitter Share Ksyen Regional Hospital - Terrace, BC on Linkedin Email Ksyen Regional Hospital - Terrace, BC link

Project Overview

People in Terrace and surrounding areas now have access to the new state-of-the-art Ksyen Regional Hospital, which opened Sunday, Nov. 24, 2024. For more, see this BC Government news release: New hospital in Terrace open for patients

The new hospital is more than twice the size of the previous facility and has 82 beds, private rooms, a bigger emergency department space, including two trauma bays, six stretcher bays, pediatric care space and four operating rooms, as well as the latest diagnostic imaging equipment.

The hospital opened ahead of schedule. Initially, construction was anticipated to be complete in 2025

Project Overview

People in Terrace and surrounding areas now have access to the new state-of-the-art Ksyen Regional Hospital, which opened Sunday, Nov. 24, 2024. For more, see this BC Government news release: New hospital in Terrace open for patients

The new hospital is more than twice the size of the previous facility and has 82 beds, private rooms, a bigger emergency department space, including two trauma bays, six stretcher bays, pediatric care space and four operating rooms, as well as the latest diagnostic imaging equipment.

The hospital opened ahead of schedule. Initially, construction was anticipated to be complete in 2025. The project cost of $633 million is being shared between the provincial government, through Northern Health, and the North West Regional Hospital District, which is contributing $120.2 million.

  • Celebrate MMH. Share your story!

    Share Celebrate MMH. Share your story! on Facebook Share Celebrate MMH. Share your story! on Twitter Share Celebrate MMH. Share your story! on Linkedin Email Celebrate MMH. Share your story! link
    supporting image

    As part of the Terrace Festival of Trees, visitors put their stories on paper decorations and hung them on an 'MMH Story Tree'.

    Let's celebrate MMH together through stories!

    Help us honour the existing Mills Memorial Hospital in Terrace and all those who have worked and received care there.

    Over the past 80 years, MMH has been part of many families’ stories – stories of joy, hope, change, and loss. As we look forward to the new hospital, we want to honour special moments that occurred at MMH.

    Win a prize!

    Names of all those who submit a story will be entered into a draw for ten $20 Tim Hortons gift cards!

    The draw will be January 31, 2024. but we will continue to collect stories after this date.

    How to submit

    Share your story. Share a memory or what you will miss most. Share a sentence or a whole page. It's up to you.

    Please include

    1. First and last name*
    2. Email
    3. Phone number
    4. Community you live in
    5. If you are Northern Health staff
    6. Photos (if you have some)

    *Let us know if you don't want your name shared with your story, but we still need your first and last name, and contact info for our records.

    Where will the stories be published?

    Northern Health hopes to share these stories on various platforms, such as:

    By submitting a story and/or photos, you are giving Northern Health permission to share these.

    We look forward to reading and sharing your stories, and celebrating the hospital together!

  • Videos promoting Terrace & new MMH

    Share Videos promoting Terrace & new MMH on Facebook Share Videos promoting Terrace & new MMH on Twitter Share Videos promoting Terrace & new MMH on Linkedin Email Videos promoting Terrace & new MMH link
    supporting image

    We've created videos promoting the new hospital and working in Terrace to help recruit staff and physicians!

    Three's three versions of the video:

    The videos are on Northern Health’s Youtube, as well as on Let’s Talk MMH, on the right side of the page under ‘Videos’.

    Thanks so much to Northern Health staff Emily Leblond, Greg Dashper and Lisette Calkins for starring in the videos.

  • Happy Holidays!

    Share Happy Holidays! on Facebook Share Happy Holidays! on Twitter Share Happy Holidays! on Linkedin Email Happy Holidays! link
    supporting image

    The holidays are just around the corner and we probably all need a little break.

    We wanted to share with you that work on the Mills Memorial Hospital construction site will slow down between December 22 and January 2. Fewer workers and less activity will be happening on site.

    Hope you stay active and healthy this holiday season! Check out a video of Spirit, Northern Health's mascot, for some fun ideas.


  • Why is there no parking at MMH?

    Share Why is there no parking at MMH? on Facebook Share Why is there no parking at MMH? on Twitter Share Why is there no parking at MMH? on Linkedin Email Why is there no parking at MMH? link
    supporting image

    We understand the parking situation at Mills Memorial Hospital is frustrating right now - for staff, physicians, patients and visitors. Not enough spots are available at certain times of the day. It’s probably taking more time to find a spot, and you likely have to walk a longer distance from your vehicle to the hospital than you’d like.

    More parking spots are coming

    We know insufficient parking has been a challenge at the hospital for a while, and the construction of the new hospital put more pressure on the situation.

    Adequate parking for patients, visitors, staff and physicians was an important consideration of the new hospital design. Parking at the new hospital will be double what it was at the current hospital, increasing from 150 to 300 spots. (And yes! Parking will continue to be free.) The majority of those parking spots won’t be ready until the middle of 2026, however, when the project is complete.

    Northern Health and PCL have come up with some creative solutions in the interim. We’ve maximized the use of the site by building temporary parking lots as space has become available. We are repainting the lines in the existing parking lots to maximize efficiency.

    The reality of the situation, however, is that parking will remain a challenge until all new spots are in place and the project is complete. And during the winter months, the situation will be even more challenging as street parking is not allowed.

    Recommendations

    There’s no perfect solution. In the meantime, we ask you to consider:

    • Arriving early
    • Carpooling
    • Getting dropped off and picked up (especially if you have mobility issues)

    Thank you for your consideration and patience during this time!

  • Alert! Tetrault Street tree row removal

    Share Alert! Tetrault Street tree row removal on Facebook Share Alert! Tetrault Street tree row removal on Twitter Share Alert! Tetrault Street tree row removal on Linkedin Email Alert! Tetrault Street tree row removal link
    supporting image

    Starting the morning of Saturday, November 11, as part of construction of the new Mills Memorial Hospital, PCL will be removing the single row of trees along Tetrault Street that start close to Haugland Avenue and end halfway to Keith Avenue.

    While this work is taking place, the parking spots that line Tetrault Street, on the east side of the existing hospital’s adjacent parking lot, will be blocked off and unavailable.

    The removal of the trees should take a maximum of two days, with the area being blocked off starting Friday night, November 10.

    The trees will be removed during the regular construction working hours of 7am to 7pm.

    The work is happening over the weekend to minimize impact on hospital parking, patients and staff. Appropriate safety precautions will be in place and the impact on neighbours and traffic should be minimal.

    Removing these trees is part of the construction of the new hospital. A landscaping plan is in place for the entire site, with garden beds planned for this area.

  • October 2023 - Quarterly Project Update

    Share October 2023 - Quarterly Project Update on Facebook Share October 2023 - Quarterly Project Update on Twitter Share October 2023 - Quarterly Project Update on Linkedin Email October 2023 - Quarterly Project Update link
    supporting image

    Download a copy of the October 2023 Quarterly Project Update.

    WHERE WE’RE AT

    Recent milestones and activities

    • In September, PCL achieved an impressive 1.5 million worker hours without a safety incident.
    • Posters with project info and featured department floors plans were displayed for two weeks in the MMH basement and Skeena Mall in Terrace. Posters are also on Let’s Talk MMH.
    • Majority of electrical panel installations are complete.
    • Food services kitchen equipment was delivered and installed.
    • Three of six elevators are complete and in use, with the final three expected to be done soon.
    • 99% of the drywalling in the entire facility is complete.
    • Site service road and new temporary parking lot in front of new Seven Sisters is now paved.
    • Startups of major systems is ongoing – for example, air handling units, heat recovery chillers, heating boiler and the steam boiler.
    • Infection control measures continue to be implemented on site - for example, boot cleaners at all entrances, daily cleaning of work areas, and use of HEPA filtered vacuums.

    Inside progress photos

    Food Services Level 0 (Basement)Laboratory Level 1 Cancer Care Level 1

    Emergency Department Level 1Sample Washroom

    WHERE WE’RE GOING


    New hospital and new Seven Sisters to open in 2024

    As the substantial completion dates for both the new Seven Sisters and the new Mills Memorial Hospital approach, the timelines for moving into the new facilities are becoming clearer.

    What substantial completion means to us is that the building is complete, and Northern Health can occupy it. It does not mean the entire MMH Replacement Project is complete. The project, including parking and landscaping, is set to be complete in 2026.

    • Substantial completion for the new Seven Sisters will occur in mid-January 2024. We anticipate moving into the new Seven Sisters in mid-February.
    • Substantial completion for the new hospital is on track for September 19, 2024. We anticipate moving into the new hospital by the end of November.

    In between the substantial completion and move in dates, staff and physicians will be oriented to the new buildings and prepare the new facilities for patient care. This includes ensuring all supplies are in place, and all systems and equipment are functioning properly, including those required to run the facility itself, and for patient care workflows and services.


    HIGHLIGHT: EMERGENCY DEPARTMENT

    Download a copy of the Emergency Department poster.

    HIGHLIGHT: INTERIOR COLOUR & MATERIALS PALETTE


    Northern Health worked with an interior design consultant to create a safe, welcoming and positive environment for staff, physicians, patients and visitors.

    Key considerations:

    • Nature
    • Northwest BC cultures
    • Northwest BC communities
    • Creation of calm, welcoming and comfortable environment
    • Promotion of health, wellness and safety
    • Department workflows and functions
    • Health standards and infection control
    • Long term maintenance, cost and availability of materials
    • Prevention of triggers


    CLOSER TO HOME CAMPAIGN UPDATE


    Thank you to all the donors who continue to come forward to make the dream of bringing a higher level of care to mothers and newborns in Northwest BC a reality.

    The Dr. R.E.M Lee Foundation’s ‘Closer to Home’ campaign is raising funds for a Tier 3 level Neonatal intensive care unit (NICU) and special care nursery at the new Mills Memorial Hospital.

    Currently, MMH's level of neonatal and maternal services is Tier 2 and no facility in Northwest BC offers Tier 3 level services.

    To learn more about and to donate to this important cause, go to remleehospitalfoundation.org or call the Foundation at 250-641-5526.
  • New hospital and new Seven Sisters to open in 2024

    Share New hospital and new Seven Sisters to open in 2024 on Facebook Share New hospital and new Seven Sisters to open in 2024 on Twitter Share New hospital and new Seven Sisters to open in 2024 on Linkedin Email New hospital and new Seven Sisters to open in 2024 link

    As the substantial completion dates for both the new Seven Sisters and the new Mills Memorial Hospital approach, the timelines for moving into the new facilities are becoming clearer.

    What substantial completion means to us is that the building is complete, and Northern Health can occupy it. It does not mean the entire MMH Replacement Project is complete. The project, including parking and landscaping, is set to be complete in 2026.

    • Substantial completion for the new Seven Sisters will occur in mid-January 2024. We anticipate moving into the new Seven Sisters in mid-February.
    • Substantial completion for the new hospital is on track for September 19, 2024. We anticipate moving into the new hospital by the end of November.

    In between the substantial completion and move in dates, staff and physicians will be oriented to the new buildings and prepare the new facilities for patient care. This includes ensuring all supplies are in place, and all systems and equipment are functioning properly, including those required to run the facility itself, and for patient care workflows and services.

  • Highlight: Emergency Department

    Share Highlight: Emergency Department on Facebook Share Highlight: Emergency Department on Twitter Share Highlight: Emergency Department on Linkedin Email Highlight: Emergency Department link
    supporting image

    Download a copy of the Emergency Department poster.


    Department features

    • On Level 1
    • Designated entrance, waiting area and registration area (separate from main entrance, waiting, registration area)
    • Significantly larger and more welcoming space
    • More patient treatment spaces
    • Patient spaces separated by walls (not curtains) improving privacy and infection control
    • Digital and in person registration desks
    • Washrooms and hand hygiene sinks throughout
    • Enclosed, heated double bay ambulance garage
    • Two team care stations with strategic sight lines that enhance patient care, and patient and staff safety


    Rendering of Emergency entrance


    Rendering of Emergency department hallway


    Download a copy of the Emergency Department poster.

  • Highlight: Interior colour & materials palette

    Share Highlight: Interior colour & materials palette on Facebook Share Highlight: Interior colour & materials palette on Twitter Share Highlight: Interior colour & materials palette on Linkedin Email Highlight: Interior colour & materials palette link
    supporting image

    Northern Health worked with an interior design consultant to create a safe, welcoming and positive environment for staff, physicians, patients and visitors. Key considerations:

    • Nature
    • Northwest BC cultures
    • Northwest BC communities
    • Creation of calm, welcoming and comfortable environment
    • Promotion of health, wellness and safety
    • Department workflows and functions
    • Health standards and infection control
    • Long term maintenance, cost and availability of materials
    • Prevention of triggers

    The colour and materials palette applies to both the new hospital and the new Seven Sisters.


  • PCL golf tournament raises $19,000 for ultrasound

    Share PCL golf tournament raises $19,000 for ultrasound on Facebook Share PCL golf tournament raises $19,000 for ultrasound on Twitter Share PCL golf tournament raises $19,000 for ultrasound on Linkedin Email PCL golf tournament raises $19,000 for ultrasound link
    supporting image

    A huge thank you to the team at PCL Construction, and all sponsors and golf teams that turned out to make the September 2023 second annual golf tournament the best ever! The event raised $19,000 towards a $72,000 Obstetrical Ultrasound for the new Mills Memorial Hospital. The equipment has now been ordered.

    Photos (from top to bottom):
    • Michael King, PCL Construction Manager congratulates Gerry Lambert, one of the Air Canada Ticket Raffle winners.
    • Derek Pearce and Michael King, PCL, present the 2023 PCL Golf Tournament proceeds, $19,000 to REM Lee Hospital Foundation Directors Roopy Kopec and Cynthia Bohn.
    • The event 50/50 Winner, David Graham from Central Painting, surprised us all by donating his $1,480 back to the Hospital Foundation! (left to right) Tania Vance, REM Lee Director, Michael King, PCL, David Graham, Anne Chisholm and Shirley Nichol, Northern Health.

Page last updated: 27 Nov 2024, 11:33 AM