As the substantial completion dates for both the new Seven Sisters and the new Mills Memorial Hospital approach, the timelines for moving into the new facilities are becoming clearer.

What substantial completion means to us is that the building is complete, and Northern Health can occupy it. It does not mean the entire MMH Replacement Project is complete. The project, including parking and landscaping, is set to be complete in 2026.

  • Substantial completion for the new Seven Sisters will occur in mid-January 2024. We anticipate moving into the new Seven Sisters in mid-February.
  • Substantial completion for the new hospital is on track for September 19, 2024. We anticipate moving into the new hospital by the end of November.

In between the substantial completion and move in dates, staff and physicians will be oriented to the new buildings and prepare the new facilities for patient care. This includes ensuring all supplies are in place, and all systems and equipment are functioning properly, including those required to run the facility itself, and for patient care workflows and services.