  • Alert! Eby/Haugland intersection reopening today

    Share Alert! Eby/Haugland intersection reopening today on Facebook Share Alert! Eby/Haugland intersection reopening today on Twitter Share Alert! Eby/Haugland intersection reopening today on Linkedin Email Alert! Eby/Haugland intersection reopening today link
    supporting image

    The Eby/Haugland intersection will be open by the end of today, Tuesday, October 25.

    After the intersection reopens, it will still need to be paved. The contractor aims to pave it sometime in the first two weeks of November, depending on the availability of local paving companies which are quite busy.

    Another section of Haugland Avenue, just west of the main hospital entrance, also still needs to be paved. Water tie-ins for this section are not yet complete, and it’s still unknown when this section will be paved.

    We will continue to post updates about road work related to the construction of the new Mills Memorial Hospital as more information becomes available.

  • Alert! Eby/Haugland intersection to be closed

    Share Alert! Eby/Haugland intersection to be closed on Facebook Share Alert! Eby/Haugland intersection to be closed on Twitter Share Alert! Eby/Haugland intersection to be closed on Linkedin Email Alert! Eby/Haugland intersection to be closed link
    supporting image

    October 19, 2021 Update
    Work took a little longer than planned but the intersection is expected to reopen at the end of this coming weekend.

    -----

    As of Tuesday, September 21, the intersection of Haugland Avenue and Eby Street will be closed for approximately three weeks, as the recently upgraded Mills Memorial hospital storm system is tied into the city’s water system.

    While some roads in the area will be closed, all traffic will be coordinated through detours and local residents will be able to access their properties.

    Visitors to the hospital are encouraged to use Tetrault Street to access the hospital while this work is underway. For those using public transportation, the Haugland Avenue bus stop, in front of the hospital, will be temporarily relocated approximately two blocks east on, towards Walmart.

    Work hours will be approximately 7am to 7pm, seven days a week.

    Please follow all signage and obey traffic personnel.

    We apologize for any inconvenience in advance but upgrading the storm and water drainage systems in the area is necessary as part of the construction of a new hospital.

    Any schedule changes will be posted on Let's Talk MMH.

  • MMH Construction Cam is online!

    Share MMH Construction Cam is online! on Facebook Share MMH Construction Cam is online! on Twitter Share MMH Construction Cam is online! on Linkedin Email MMH Construction Cam is online! link
    supporting image

    An MMH construction cam is now available to the public!

    That means any day, any time, you can see where construction of the new hospital is at.

    On the construction cam link you zoom around the site, view past photos, and compare photos of different days. You can also view and download time lapse videos.

    The link has views and photos, from two video cameras mounted on the roof of the current hospital. One view faces north, overlooking the tower cranes and construction of the new hospital. The other view faces west, overlooking the future site of the new Seven Sisters facility.

    The cameras takes photos every fifteen minutes.

    Check the MMH construction cam. Play around!





  • Alert! Upcoming road work near hospital

    Share Alert! Upcoming road work near hospital on Facebook Share Alert! Upcoming road work near hospital on Twitter Share Alert! Upcoming road work near hospital on Linkedin Email Alert! Upcoming road work near hospital link
    supporting image

    More road work, related to the construction of the new Mills Memorial Hospital, is coming down the pipe.

    Last month, upgrades were made to the storm and water system under Haugland Avenue west of the hospital’s main entrance towards Eby Street.

    In addition, a secondary water main, under Tetrault Street needs to be installed. This should take about three days during which a section of Tetrault Avenue near Keith Avenue, will be closed.

    Residents will still be able to access the businesses on the corner of Keith and Tetrault. However, drivers won’t be able to drive through Tetrault from Keith Avenue, or onto Keith Avenue.

    The work on Tetrault work should begin Saturday, August 28, and will take approximately 3 days.

    Similar to when upgrades were made under Haugland Avenue, a section of Tetrault, after the initial upgrades are made, will remain a gravel surface. That section will be paved after the contractor can do the final connection to the water main based on approved tie in procedures.

    PCL is working closely with the City of Terrace and its permitting approval process while planning and completing this work. Plans are in place to mitigate neighbourhood and community impacts including managing dust and traffic disruptions.

    Water system upgrades on Haugland avenue are almost complete.

    Paving the section of Haugland Avenue near Eby.



  • Attaching tower crane's jib to its mast

    Share Attaching tower crane's jib to its mast on Facebook Share Attaching tower crane's jib to its mast on Twitter Share Attaching tower crane's jib to its mast on Linkedin Email Attaching tower crane's jib to its mast link
    supporting image

    Workers, strapped in for safety, wait for the jib to be lifted into place.

    Mobile crane lifts jib into the correct position of the tower crane's mast.

    Workers place the jib.




  • Interested in work and/or contract opportunities?

    Share Interested in work and/or contract opportunities? on Facebook Share Interested in work and/or contract opportunities? on Twitter Share Interested in work and/or contract opportunities? on Linkedin Email Interested in work and/or contract opportunities? link

    Many residents and businesses have been asking about employment and contract opportunities related to the Mills Memorial Hospital project. PCL Westcoast Constructors Inc (PCL) is responsible for all employment and contracting related to the construction of the new hospital.

    Employment

    Anyone interested in working on the project can submit a resume to PCL through https://careers.pcl.com/ca/en

    PCL, through their subcontractors has, and will continue to, advertise employment opportunities on and in various platforms such as Linkedin, Kijiji, and regional newspapers.

    The project is dedicated to employing as many locals as possible and has already hired a number of local equipment operators, tradesmen and labourers. They have also been reaching out to local and regional First Nations, to meet with employment and training departments, as well as the trades department at the college.

    Contracts

    Since before construction began, PCL has been reaching out to local and regional companies to explore the possibility of working together.

    Throughout the project, PCL will share contract opportunities as they come up - for example, by advertising in the regional newspaper, or contacting potential local and regional suppliers directly.

    Businesses interested in working on the Mills Memorial Project site are encouraged to contact PCL with information about services they could offer. Email PCL at 2220057millsmemorial@pcl.com

    Still not sure what to do?

    Email letstalkMMH@northernhealth.ca and we’ll put you in the right direction.

  • What's that in the sky?

    Share What's that in the sky? on Facebook Share What's that in the sky? on Twitter Share What's that in the sky? on Linkedin Email What's that in the sky? link
    supporting image


    The tower cranes at the MMH construction site can be seen throughout the community.


    It’s a bird. It’s a plane. No. It’s two tower cranes!

    In the next couple weeks, two 160-foot tower cranes will be erected at the Mills Memorial Hospital site and remain on site – and in the Terrace skyline – for approximately 18 months. To put the height of the cranes into perspective, 160 feet is approximately 50 metres, which is the length of three and half semitrailers in a row.

    Tower cranes are made up of a vertical tower (the mast) and an outstretched jib (the working arm). They are used on major construction sites to lift and move heavy equipment and materials.

    It will take about four days to assemble and erect the two cranes, which will be permanently attached to concrete bases, which were built over the last month in anticipation of the cranes’ arrival.

    The mobile crane, which has been on site for several weeks, will be used to assist in the set up of the tower cranes.

    All the cranes will only work within the perimeter of the construction site. The tower cranes will be located in what will be the interior of the new building and the jibs won’t be able to reach outside of the property limits.Start of tower crane erection on August 4, 2021.

  • Smooth progress

    Share Smooth progress on Facebook Share Smooth progress on Twitter Share Smooth progress on Linkedin Email Smooth progress link
    supporting image

    The Mills Memorial Hospital Replacement project is progressing smoothly. Two major activities on the go right now include upgrades to the storm and water system on Haugland Avenue, near Eby Street and a large concrete pour with two pumps working on site today, Monday, July 26.


    Double pumping concrete action.







  • Alert! Road closure near hospital

    Share Alert! Road closure near hospital on Facebook Share Alert! Road closure near hospital on Twitter Share Alert! Road closure near hospital on Linkedin Email Alert! Road closure near hospital link
    supporting image

    The section of Haugland Avenue, between Eby Street and the nearest hospital entrance (see photo for exact location), will be closed for approximately two weeks starting this Saturday, July 24, as storm and water drainage systems are upgraded as part of the construction of a new Hospital.

    Only pedestrians and local residents with private driveways on the north side of Haugland will be able to access the area while work is underway. The area will be closed to drivers and cyclists from the general public.

    We suggest anyone driving to and from the hospital, use Tetrault Street.

    Please follow all signage and obey traffic personnel if you are in the area.

    For more information about the upgrades, go to:

    https://letstalk.northernhealth.ca/mills-memorial-hospital-replacement/news_feed/haugland-closure


  • New, temporary parking lot near Tetrault

    Share New, temporary parking lot near Tetrault on Facebook Share New, temporary parking lot near Tetrault on Twitter Share New, temporary parking lot near Tetrault on Linkedin Email New, temporary parking lot near Tetrault link
    supporting image

    A new parking lot on the east side of the Mills Memorial hospital site, which fits approximately 70 vehicles, is now available for use.

    The new gravel lot, adjacent to Tetrault Street and north of the hospital, aims to accommodate a growing number of hospital staff and reduce street parking. Because of its distance to the hospital entrance, the new lot is intended mainly for staff use. However, the spots have no restrictions.

    This lot is temporary and will be removed when the area is required to accommodate the building of the new hospital – likely in the summer of 2023.