Changes to procurement plan

November 2019

We are working through some changes in the initial procurement plan because there were no acceptable bids for the Seven Sisters RFP (Request for Proposals). The bids received were higher than anticipated in the project budget and projected schedules longer than allowed for construction.

The Seven Sisters replacement project has been added to the Request for Qualifications/RFP processes for the overall MMH redevelopment project, but we are still maintaining the project timelines. Adding the Seven Sisters project into the overall MMH redevelopment improves the likelihood that timeline and budgetary expectations are met by allowing one contractor to plan, schedule and construct both Seven Sisters and the new MMH.

The Project Office for the MMH replacement will be located in Terrace (address TBD) and recruitment continues for dedicated roles. Additional roles are being added to Northern Health Careers over the next few weeks.

Categories: #procurement
Share Changes to procurement plan on Facebook Share Changes to procurement plan on Twitter Share Changes to procurement plan on Linkedin Email Changes to procurement plan link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>