June Progress Photos

The new Dawson Creek & District Hospital is really starting to take shape!

Concrete pours for the suspended slabs will be complete by the end of July and over 7,510m3 of concrete will have been poured for all three levels. Over the coming weeks and months, workers will begin removing the shoring which is the vertical tower support system that carries the weight of the formwork, reinforcing bar, concrete and live loads. Work is also underway for waterproofing and backfilling the perimeter of the building.





Categories: Photos, Construction Progress
Share June Progress Photos on Facebook Share June Progress Photos on Twitter Share June Progress Photos on Linkedin Email June Progress Photos link