Bulk excavation and increased truck traffic
There has been an increase in truck traffic on and around the site due to bulk excavation for the hospital basement starting. Excavation will continue for the next 4-5 weeks. Trucks will be entering the site from 112 Ave and exiting the site from 12 St.
Fun fact: Currently, approximately 12 trucks are entering and exiting the site per hour and removing approximately 1800m³ of material per day! In the next week, this will increase to approximately 20 trucks per hour removing up to 2500m³ of material per day. Once bulk excavation is complete, approximately 56,000m³ of material will have been removed from the site.