  • SLH Business Plan Progress

    Share SLH Business Plan Progress on Facebook Share SLH Business Plan Progress on Twitter Share SLH Business Plan Progress on Linkedin Email SLH Business Plan Progress link

    The business plan phase - now underway - will finalize details such as scope and budget for the replacement of Stuart Lake Hospital. This stage takes approximately 12 to 18 months – current planned submission for review by government is end of 2019

    When the Business case has been developed and completed the plan will be submitted to government for scope and funding approval. Upon completion of Business Planning the project will move into procurement followed by construction. All costs will be finalized in the business planning phase.