February 2023 Quarterly Update

Where we’re at

Despite the ups and downs in temperature, through snow and wind, and on the occasional welcome sunny day, construction continues to advance at the site of the new Stuart Lake Hospital. Staff, patients, and visitors to the hospital have seen great change from the windows, as we’ve gone from a spruce forest to a forest of rebar and concrete. From a hole in the ground back in the fall to foundations, walls and miles of orange tarp, the replacement hospital is becoming a reality.

Weather hoarding and tarping of work surfaces for concrete pours continues, and waterproofing and damp proofing work is ongoing. Suspended slab pours began in November and continue when the weather permits. Despite a closure from December 24 to January 4, progress is right on track with below grade utilities and site services infrastructure. Structural Steel fabrication is underway and we happily anticipate site work starting mid-February.

Project schedule

Like all project schedules, timelines can be impacted by any number of factors and thus are subject to change. That said, the SLH replacement project is on time in terms of overall construction and design.

The 100% Design Submittal has been under review by Northern Health since its submittal in November 2022. Graham recently delivered a supplement 100% Design Submittal which has been reviewed by NH and sent back with comments.

If all goes as planned, the current schedule sees the building substantially watertight by this fall. This means we’ll be on schedule for the opening and operation of the new hospital in 2024. This will be followed by the demolition of the old hospital, and the creation of new parking and culturally significant gardens and landscaping in its stead, and project completion in 2025!

Next steps and upcoming milestones

Engagement

New renderings from the 100% Design Submittal are expected in the next few weeks so we can better picture the hospital as it will appear in real life. Renderings are subject to change, but as engagement ramps up in the new year, opportunities will arise for the public to take a peek at the prospective hospital design. It will also allow us to hear what you say, gather feedback, and deliver it back to the project team.

We are very excited for 2023’s community engagement opportunities. Some of these will include:

  • Public displays at multiple locations in Fort St. James where people can view the renderings and plans for the new hospital
  • A joint event at Fort St. James Senior Secondary School with NH Recruitment to introduce students to employment pathways in health and the many opportunities that will exist in the new hospital
  • Open houses for health care workers and the public (dates and venues yet to be determined) in Nak’azdli and Fort St. James. These will be a highlight of our engagement year and a chance to connect in person
  • Health and education fairs, community or employment event? We are available! And we’ll travel. Get in touch if you’d like us to present to your organization or be present at your event.

For more information

Employment Opportunities at SLH

A new hospital with more beds, expanded lab and diagnostic imaging, and a Primary Care Clinic means a great number of positions to fill. Jobs in housekeeping, food services and maintenance will be available, as well as technician positions, nurses and care aids, to mention only a few.

With construction underway, we are thinking about how to staff the new facility to ensure that health needs of the community are met. We are also thinking about the benefits of staffing the hospital from the community – some people are credentialed and ready to go into the positions available, and some are looking to start down the path to employment, and a new hospital is a great opportunity for all.

To start your education journey to a job in health care, connect with employment contacts at Northern Health Recruitment or contact the Stuart Lake Hospital Site Manager. Go to Let’s talk to discover what jobs are available and how to access the education and support to get you there.

Stuart Lake Hospital Replacement Project Let’s Talk

Let’s Talk is our one-stop shop for everything related to the Stuart Lake Hospital project. Not only does this site have regular project updates, but it is also a place where you can provide feedback and thoughts on the project. We are always looking to connect and to hear from you! Please stay in touch and keep your questions coming.

Stuart Lake Hospital Let’s Talk

Stuart Lake Hospital Replacement Project construction camera

We’ve installed a construction camera that you can access to see what’s going on at the site! Follow along to see the progress and watch the new hospital take shape.

Click on the link on the Let’s Talk Page (or here: Stuart Lake Hospital Construction Camera) for a bird’s eye view of construction anytime you like.

Contact us directly

For questions, feedback, or to get added to the distribution list for these updates, feel free to reach out directly to us at:


LetsTalkSLH@northernhealth.ca

Categories: Important Information, Photos, Quarterly Update, Progress, Construction, Design
Share February 2023 Quarterly Update on Facebook Share February 2023 Quarterly Update on Twitter Share February 2023 Quarterly Update on Linkedin Email February 2023 Quarterly Update link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>